TITLE Supreme Court en banc Decision 2014Da235189 Decided October 30, 2018 【Construction Payment】 [full Text]
Summary
In a long-term continuing construction contract under Article 21 of the former Act on Contracts to which the State is a Party, where the total construction period is extended beyond the construction period additionally stated in the initial agreement, whether the adjustment of contract amount is allowed on the ground of a change in construction period (negative)
Prev Supreme Court en banc Judgment 2013Da61381 Rendered October 30, 2018【Damages (Others)】
Next Supreme Court en banc Decision 2018Do7172 Decided October 30, 2018 【Violation of the National Sports Promotion Act (Opening of Gambling Parlors, Etc.); Operation of Gambling Establishment; Violation of the National Sports Promotion Act (Gambling, Etc.); Regular Gambling; Inciting Violation of the Credit Information Use and Protection Act; False Testimony】